Englewood will not issue a right-of-way permit until this bond or another approved form of security is on file. The amount is tied to your job, not a flat figure, so getting it right up front keeps your permit from stalling at the counter.
Under Englewood Municipal Code 11-7-9, anyone pulling a permit for work in the City of Englewood right-of-way must file a bond or letter of credit in favor of the city for the total cost of construction, including labor and materials, or $5,000, whichever is greater. The bond must stay in force for at least two years after the city accepts the work, which matches the two year warranty in Section 11-7-10.
We can help with all Colorado bonds!
There is no single amount. Section 11-7-9 sets the bond at the total cost of construction, labor and materials included, or $5,000, whichever is greater. A $3,000 curb repair still needs a $5,000 bond. A $60,000 utility trench needs $60,000. The permit application asks for an itemized estimate of restoration cost to set the bond, and the city can raise that estimate if it looks low compared with recent bids the city or CDOT has received for similar work.
Section 11-7-4 requires a city contractor license for any work in the right-of-way and a permit for each job, and permits go only to licensed and bonded contractors or to a homeowner at their own primary residence. Before any permit is issued, the applicant files this bond or a letter of credit.
There are a few exceptions. Public utilities, franchised entities, and metropolitan, water and sanitation districts working in the city may file a letter of responsibility instead. The city may also waive the bond, or accept one without a surety, if it finds the applicant has the financial stability and Colorado assets to cover claims. Emergency repairs may begin without a permit, but a permit must be applied for by the second working day if right-of-way improvements are disturbed.
The bond is conditioned on full compliance with city ordinances, rules and regulations, and on payment of judgments and costs for damages from negligent or wrongful acts in the permitted work. The city can sue on the bond for itself or on behalf of anyone harmed. The city must approve the bond form and the surety before the permit is issued.
By accepting the permit, the contractor warrants the work for two years from the city's initial acceptance. That covers defective workmanship, settling of fills or excavations, unapproved deviations from plans, failure to barricade and failure to clean up. Emergency repairs must be made within 24 hours and other repairs within 30 calendar days of notice. If the contractor does not fix the problem, the city does the work and bills the actual cost plus a 50 percent penalty. The bond must remain in force at least two years after completion and acceptance. About 30 days before the warranty ends, the city inspects the work and releases the bond if it passes.
Section 11-7-8 also requires commercial general liability with XCU coverage of at least $2,000,000 per occurrence and $4,000,000 aggregate, plus workers compensation.
The premium is a percentage of the bond amount, so it scales with the size of the job. The surety sets the rate after reviewing the contractor's credit and history.
Take the total cost of construction, including labor and materials, and compare it to $5,000. The bond is whichever number is larger. The city can raise your cost estimate if it seems low compared with recent bids for similar work.
At least two years after the work is completed and accepted by the city. The city inspects about 30 days before the two year warranty ends and releases the bond if the work is still in good shape.
Yes. Section 11-7-9 allows a bond or a letter of credit in favor of the city. Public utilities, franchised entities and metro, water and sanitation districts may file a letter of responsibility instead.
The city can make the repairs itself and bill you the actual cost plus a 50 percent penalty, due within 30 days. Unpaid costs can be recovered from the bond.
The premium is a percentage of the bond amount, so a larger job means a larger premium. The surety sets the rate from your credit and business history.
This website is a referral and marketing platform that connects users with licensed insurance agents. We do not issue surety bonds directly except in states where we are licensed. All bond applications are processed and fulfilled by licensed agents. By using this site, you agree to our Terms & Conditions, Privacy Policy, and the use of cookies. If you do not agree, please exit the site.