Most contractors expect one flat Harris County right of way bond amount. There isn't one. The County Engineer sets the bond by the work you are doing, with a $5,000 minimum per crossing and higher figures for linear footage, traffic signals and road work. Get the amount and the Harris County bond form right on the first submission and the notification can go straight into the county's 10 business day review.
Harris County requires a surety bond on its own bond form with every Notification of Construction in the Right of Way. The amount is calculated: a minimum of $5,000 per right of way crossing, $8 per linear foot for work other than irrigation, $2 per foot for irrigation lines, the greater of $80,000 or 100% of construction cost per traffic signal, and the greater of $40,000 or 100% of construction cost per median modification, turn lane, road widening, storm sewer bore, tunnel or roadway open cut. Contractors must post a new bond for each project. Perpetual bonds are reserved for public utility companies and engineering firms filing for them.
We can help with all Texas bonds!
The Harris County Office of the County Engineer lists minimum bond amounts by type of work, not a single figure:
If your plans include more than one of these items, ask the Public Review Group how they combine before you request the bond, so the amount on the bond matches what the county will accept.
The county requires a notification whenever an individual, contractor or utility company plans to work in Harris County right of way. The examples it gives are non-residential sidewalk construction, roadway paving, left turn lanes, median openings, and utility crossings, repairs or connections for waterlines, sewer lines and pipelines. The contractor submits the notification together with the bond.
The county states that a contractor must use a new bond and that an existing bond will not be accepted. Perpetual bonds are available only to public utility companies and to engineering firms submitting on behalf of public utility companies. The County Engineer also runs separate Flood Control District right of way notifications, with their own standard and perpetual bond options.
The bond must be written on the Harris County bond form, with the surety's power of attorney attached and seals that are embossed or raised. The notification and bond can be filed through the county's e-Permits system or delivered by mail or in person. The county targets 10 business days for processing, the permit is valid for 6 months, and plan review and inspections are required. Fees are set by the county fee schedule and confirmed in the approval email.
After construction, the contractor submits an Initial Inspection Request for work in Right of Way. The final inspection must be requested 90 days prior to the expiration date on the bond. Ask for a bond term that leaves room for that window. The governing rules are the county's Construction in Harris County or Harris County Flood Control District ROW Regulations. Questions go to the Public Review Group at (713) 274-3931.
It depends on the work. The county minimums are $5,000 per right of way crossing, $8 per linear foot other than irrigation, $2 per foot for irrigation lines, the greater of $80,000 or 100% of construction cost per traffic signal, and the greater of $40,000 or 100% of construction cost per median modification, turn lane, road widening, storm sewer bore, tunnel or roadway open cut.
No. The County Engineer states that you must use a new bond and that an existing bond will not be accepted.
Harris County offers perpetual bonds to public utility companies and to engineering firms submitting on behalf of public utility companies. Ask the Public Review Group which form applies before the bond is issued.
The Harris County bond form. Attach the surety's power of attorney, and make sure the seals are embossed or raised. A bond on a generic form is not what the county asks for.
The notification permit is valid for 6 months, and the final inspection must be requested 90 days prior to the expiration date on the bond. Choose a bond term that covers construction plus that inspection window, and confirm it with the county when you file.
This website is a referral and marketing platform that connects users with licensed insurance agents. We do not issue surety bonds directly except in states where we are licensed. All bond applications are processed and fulfilled by licensed agents. By using this site, you agree to our Terms & Conditions, Privacy Policy, and the use of cookies. If you do not agree, please exit the site.