Commerce will not issue a land disturbance permit until the per acre security is in place. A surety bond covers that $3,000 per acre obligation for an annual premium, so the cash a developer would otherwise lock up in an escrow account or letter of credit stays available for grading, utilities and the rest of the job.
The City of Commerce, Georgia requires a Land Disturbance Bond equal to $3,000 per acre of land disturbing activity before a land disturbance permit is issued. The city accepts a security bond, irrevocable letter of credit, escrow account, or a combination. If site activities fall out of compliance with city standards and are not corrected within 30 days, the city can call the bond and hire a contractor to stabilize the site.
We can help with all Georgia bonds!
The bond is not a flat figure. The City of Commerce Land Disturbance Permit Application calls for a Land Disturbance Bond in an amount equal to $3,000 per acre. A 5 acre site needs $15,000 of security, a 20 acre site needs $60,000. That matches the ceiling in state law, since O.C.G.A. 12-7-7 lets a local issuing authority require security of up to, but not exceeding, $3,000 per acre of the proposed land disturbing activity before the permit issues.
The city's application is direct about it. If activities on the site do not comply with City standards and policies within 30 days, the city will call the bond and hire a contractor to stabilize the activity. The state statute gives the same remedy, allowing the issuing authority to use the proceeds to stabilize the site. The surety pays a valid claim and then recovers that amount from the developer or contractor who posted the bond.
The Commerce application package also asks for a receipt showing fees paid to Georgia EPD, a copy of the Notice of Intent, and a current GSWCC Level 1A Fundamentals certification card or higher for the person conducting grading on the project. Holding the certification does not replace the bond. Bonds are reviewed by the Commerce Planning and Development Department and the City Attorney for compliance, and the City of Commerce fee is due after the plans are reviewed and approved.
Confirm the disturbed acreage on your approved plans, since that drives the bond amount, and ask the Planning and Development Department whether the city uses its own bond form.
The Commerce application sets it at $3,000 per acre of land disturbing activity. Multiply the disturbed acreage on your plans by $3,000.
Yes. The city accepts a security bond, an irrevocable letter of credit, an escrow account, or any combination of those.
If site activities do not comply with City standards and policies within 30 days, the city can call the bond and hire a contractor to stabilize the site.
No. The certification card is a separate requirement for the person running grading operations. The bond is still required.
You pay a premium based on the bond amount and the credit and financial strength of the applicant. You see the quote when you apply.
This website is a referral and marketing platform that connects users with licensed insurance agents. We do not issue surety bonds directly except in states where we are licensed. All bond applications are processed and fulfilled by licensed agents. By using this site, you agree to our Terms & Conditions, Privacy Policy, and the use of cookies. If you do not agree, please exit the site.